Executive Summary:
On October 9, 2026, the Federal Energy Regulatory Commission (FERC) issued its order on PJM’s large load filing. This framework, which we covered in August, introduced the Interim Resource Adequacy Service (IRAS) and the Bring Your Own New Capacity (BYONC) pathways. FERC accepted PJM’s 50 MW Large Load definition and its new Large Load Registry, but rejected IRAS, BYONC, and the related capacity market design changes as filed.
For storage and renewable asset owners and developers, the headline sounds like a setback; however, the broader picture is more encouraging. FERC acknowledged the imminent capacity shortfall in PJM, left the door open for a revised proposal, and pointed to state-level regulators to help solve the large load problem. The demand for new capacity that made BYONC so attractive is still real. What has changed is the path to solve this growing problem.
This article outlines FERC’s decision, what still stands, and how asset owners can stay positioned while PJM and its member states rebuild the framework.
This article covers topics that include:
(click to skip ahead)
What FERC Decided
FERC divided PJM’s filing into two parts: the data infrastructure it accepted and the capacity framework it rejected.
As of October 12, 2026, the following elements have been accepted:
- Large Load Definition: An end-use load with a cumulative peak demand of 50 MW or more at a single site.
- Large Load Registry: A central database used to track each large load’s location, ramp schedule, capacity supply, and other details. FERC agreed the registry will help PJM to forecast load growth and transmission buildout requirements. PJM is required to submit a compliance filing within 30 days of the order.
FERC rejected the following items:
- The Interim Adequacy Service (IRAS)
- The requirement for New Large Loads to find new capacity
- The BYONC rules that would have allowed large loads to avoid IRAS curtailment
- The exclusion of New Large Loads from the capacity auction demand curve
What’s important to note is that FERC did not say large loads should be exempt from bringing capacity, and it did not dispute that PJM faces a critical supply shortage. It found that the mechanism proposed by PJM either reached beyond its authority or was not sufficiently supported.
Why FERC Pushed Back
FERC’s pushback is centered on three main issues, each of which has implications for asset owners looking to contract with large loads.
1. Federal vs. State Jurisdiction
Most large loads, including data centers, are considered retail customers of state-regulated utilities. FERC found that IRAS provisions assigned obligations directly to those retail customers, overstepping its jurisdiction. Although IRAS shifted some responsibilities to electric distribution companies (EDCs), FERC concluded that it did not assign enough – specifically, PJM’s ability to dictate which retail customers could be curtailed and an effective retail rate through the proposed compensation sections of IRAS.
2. Treatment of New Large Loads
FERC also found that PJM did not provide sufficient evidence to justify the treating of utilities and Load Serving Entities (LSEs) serving New Large Loads differently from those that are not, especially since each recovers the same network transmission service charges from those retail customers. Under the Federal Power Act, rates and terms of service cannot be discriminatory.
3. Capacity Accreditation
In our August article, we noted that a BYONC arrangement would have locked in the resource’s Accredited UCAP from the first Delivery Year, protecting the large load from future declines in the resource’s ELCC. FERC found that PJM’s proposal to lock in that accreditation value unsupported. The takeaway for asset owners is that ELCC exposure risk must be considered in any future bilateral capacity agreements.
In addition to the key issues mentioned above, FERC also flagged other items PJM should consider revisiting should they choose to submit a revised filing. One such issue FERC flagged was related to the “deliverability” of BYONC resources with New Large Loads. PJM’s BYONC filing allowed for any BYONC resource in the PJM footprint to contract with any New Large Load within PJM, regardless of location. FERC suggested PJM should reconsider whether BYONC resources be required to be in the same Locational Deliverability Area (LDA) as the New Large Load it is contracting with. This is an important consideration for asset owners, as a future BYONC proposal may require BYONC resources and New Large Loads to be within the same LDA.
What Hasn’t Changed
FERC’s order still favors new storage and renewable capacity in PJM in several ways.
- Supply Shortage: PJM’s last two Base Residual Auctions cleared short of the reliability requirement, with the 2028/29 BRA coming in more than 6 GW below PJM’s target. In addition, PJM expects up to 70 GW of large load additions by 2038. FERC stated plainly in its order that it recognizes this capacity shortfall.
- Capacity Prices: Without IRAS and BYONC to curtail or exclude large loads, this new demand remains in the market. This could mean higher capacity prices for a longer period, which benefits the resources that are operating and participating in these markets.
- RBP: FERC conditionally approved PJM’s Reliability Backstop Procurement earlier this month. Once finalized, this will provide a separate mechanism for long-term capacity revenue for new resources.
The Rules Are Changing, but Opportunities Still Exist
Demand for new capacity in PJM is still growing, even as the framework for contracting is being rebuilt. SYSO keeps assets qualified, performing, and market-ready, so you are positioned for whatever framework comes next. Need more information?
What Comes Next
Asset owners should be prepared for several possibilities
1. PJM Revises and Refiles
PJM has stated it is reviewing the order to determine how it can meet FERC’s requirements while respecting the jurisdictions of the states and protecting existing customers from bearing the costs of new large loads. FERC explicitly allowed PJM to submit an alternative proposal. A revised filing is likely to keep the Large Load Registry at its center and leave curtailment decisions to the states.
2. States Get Involved
FERC encouraged states to continue their own work on large load policy. Specifically, which retail customers would be curtailed when the system is stressed, arguing that non-critical data centers should be curtailed before homes, hospitals, and schools, and only after voluntary demand response is exhausted.
3. Combined Ruling
A likely outcome is a combination of PJM tariff provisions, state utility commission orders, and EDC tariffs. Under this possibility, requirements for large loads would vary by zone, creating more variables for asset owners participating in the market.
What Asset Owners Can Do Now
Regulatory processes take time. Preparing your asset for the new anticipated framework can offer great upside. Here are some practical steps you can take:
- Model Accreditation Risk: With FERC rejecting the fixed accreditation model, run your revenue model against a range of ELCC outcomes. Be ready to address how accreditation value changes are shared in bilateral agreements.
- Monitor State Policies: State commission proceedings across the PJM footprint may define curtailment priorities and contracting requirements for large loads in each zone. Monitor new developments closely and be prepared to include them in your models.
- Consider RBP: FERC recently approved much of PJM’s proposed Reliability Backstop Procurement, though it delayed implementation up to five months to allow PJM to address deficiencies related to cost allocation. This delay in the RBP, coupled with the uncertainty around the future of BYONC, creates an opportunity for developers to reassess whether participating in RBP is a better fit for their assets.
How SYSO Can Help
FERC’s order is a reminder that capacity revenue can be influenced by federal, regional, and state policy. SYSO provides market participation services in PJM for storage and renewable assets, including scheduling, 24/7 NOC services, telemetry, and market settlement. Our team has a deep understanding of PJM’s capacity market and follows FERC, PJM, and state proceedings closely, so our clients can focus on building and operating their assets while we track what the next framework will require. Whether PJM’s revised proposal arrives in months or the answer comes from the state commissions first, we help our clients keep their assets qualified, performing, and ready to contract. Contact us today to discuss how SYSO can help you navigate PJM capacity market complexity.